Project
License for Khimti 1
HPL's
Main Site at Kirne
|
|
HMGN
has issued to Himal Power Limited a Project License to build,
own, operate and transfer the Khimti I Hydropower Project.
The Project License gives HPL the right of uninterrupted
flow of the water of the Khimti River to the Project. According
to which HMGN shall not issue any other permits for use
of water in the catchments area that will impair the flow,
specified in the Project License.
|
Project
Agreement with HMGN
His
Majesty’s Government of Nepal and Himal Power Limited entered
into a Project Agreement concerning Khimti 1 Hydropower Project
on 17th of Chaitra 2050 (30th March 1994).
Power
Purchase Agreement
|
Nepal
Electricity Authority and Himal Power Limited entered into
a Power Purchase Agreement concerning the Khimti 1 Hydropower
Project on 17th of Chaitra 2050 (30th March 1994) for a
twenty (20) years period commenced on the Commercial Operation
Date - 11th July 2000 (Ashad 27, 2057).
|
|
Kimti
River
|
Transfer
of Interest to NEA
Upon
the expiration of the PPA period, HPL will transfer to NEA of
a fifty percent (50%) ownership interest in the Project for a
nominal consideration of one (1) Rupee. Such ownership interest
will be structured as a joint venture between HPL and NEA. At
the end of the fifty (50) years period of the Project Licence,
HPL shall transfer the Project free of charge to HMGN.
| Project
Ownership
|
|
|

Khimti I Contorl Room Building and 132kv Terminal Tower
|
|
The
Project shall be built, owned and operated by HPL in accordance
with the terms and conditions of the Project License. At
the end of the fifty (50) years period of the Project License,
HPL shall transfer the Project free of charge to HMGN.
|